Site Remediation, Buckinghamshire

31st May 2017

Telluric Land Remediation completes contaminated land cleanup in Aylesbury Vale

ISCOWe have recently completed a ground remediation project on a housing development site in Aylesbury Vale, Buckinghamshire.  This former paint factory site had two areas of contamination, one containing metal contamination and another larger area with organic contaminants including petroleum hydrocarbons, naphthalene, chloroethene and methyl benzene. The small volume of metal contaminated soil was removed from site to a disposal facility whereas the organic contamination was treated in-situ, initially by pump & treat, to remove grossly contaminated groundwater, and then by chemical oxidation. After 14 weeks of remediation work the Regulators were satisfied that the housing development could commence.